Good project preparation in the spotlight as FIDIC-CICA webinar series concludes

05 Oct 2026

news image

The third and final event in FIDIC's 2026 webinar series with the Confederation of International Contractors' Associations (CICA) took place on 1 October 2026, focusing on why the decisions taken before a contract is signed so often determine whether a construction project succeeds. 

The webinar, The Good Preparation of Construction Projects, attracted around 700 registrations from across the global infrastructure community.  

The session was co- moderated by Fanny Dastugue, director general of CICA, and Daduna Kokhreidze, FIDIC's chief legal and contracts officer. Speakers included Jocelyne Jabbour, senior governance specialist at the World Bank in the USA; Enea Sermasi, head of international business development at Politecnica Ingegneria ed Architettura in Italy; Stefan Ciufu Hayward, legal and compliance director for Britain and Ireland at Colas; Adriana Spassova, partner at EQE Control OOD in Bulgaria and a member of the FIDIC Contracts Committee; Mariam Badeyan, chief legal officer at AAB Construction in Armenia; Asel El Housan, manager of AEH UK Limited Engineering & Claim Consultancy; and Aisha Nadar, arbitrator at Advokatfirman Runeland AB in Sweden. 

The panel brought together the perspectives of funders, contractors, employers and consultants. The group discussion started with a unanimous premise that decisions made at the very start of a project, defining objectives, allocating risk, engaging stakeholders and choosing the right consultants and form of contract can shape its entire life and help avoid disputes later on. 

Offering a contractor's perspective, Stefan Ciufu Hayward set out three foundations of good preparation: a shared understanding among all parties of the project's scope, objectives, programme and constraints; early identification of technical, commercial and operational risks, allocated to the party best placed to manage them; and the right delivery team on every side. He also highlighted early contractor involvement as an effective way of testing whether an employer's objectives can realistically be delivered and of managing risk before tender. 

Asel El Housan argued that many projects fail even earlier, through inadequate feasibility studies, unsecured funding or a lack of clear leadership on the employer's side. She stressed the importance of choosing a procurement strategy suited to the nature of the works, recalling an employer that proudly selected the Silver Book for a five-star hotel without a detailed design, and urged employers to treat consultants, designers and contractors as partners. 

Speaking from the employer's side, Mariam Badeyan said preparation begins when the employer defines what it actually wants to achieve, long before procurement documents are drafted. Land acquisition, permits, utility relocation and the question of who will own the design all shape the procurement strategy, she explained, concluding that a good contract is the result of a well-prepared project rather than its starting point. She also observed that preparation is often underestimated because it does not look like progress, yet two or three extra months spent testing assumptions can save a year or more during delivery. 

Aisha Nadar emphasised that employers own the project objectives and must do their homework before taking key decisions on scope, site, financing, risk and the content of the procurement package. FIDIC contracts allocate identified risks effectively, she said, but a contract cannot acquire land, provide financing or guarantee an effective Engineer, and risks that were never identified may never have been contemplated. She cited Boston's "Big Dig" as an example of how underestimated site conditions led to disputes and years of delay. 

Adriana Spassova pointed to recurring mistakes before contract signature, including contract forms chosen without regard to sound risk allocation principles, such as Yellow Book contracts for metro and motorway projects in Bulgaria that transfer ground risk to the contractor and consultants selected on lowest price or given restricted authority as the Engineer. She noted that many disputes she sees as an adjudicator stem from defective technical documents, citing Bulgaria's first high-speed rail project, planned for two years but delivered in ten, and recommended establishing a "single source of truth" for project records from the outset. 

From a funder's perspective, Jocelyne Jabbour explained that the World Bank assesses project readiness across several dimensions: institutional capacity and decision-making authority, a well-defined but not over-prescriptive scope, clear risk identification and allocation, realistic cost estimates with appropriate contingencies, and legal and regulatory readiness, including land, permits and environmental approvals. She stressed the importance of documenting preparatory work and outlined the World Bank's early market engagement (EME) requirement, mandatory since March 2025 for World Bank-financed international procurements above US$10 million. Conducted transparently and fairly, she said, EME helps clients test specifications, packaging, contract type and risk allocation against market reality, moving from a "post and hope" approach to one informed by market intelligence. 

Enea Sermasi described a construction project as a table that needs three legs: construction, contract administration and design stewardship. He contrasted two healthcare projects financed by a multilateral bank under the FIDIC Red Book – one tendered on an outdated, unvalidated design that triggered claims and a significant extension of time, and another where an independent validation of the design, an experienced procurement team and a short gap between validation and tender put the contract on solid ground. He proposed a simple three-question test of design maturity, how old is the design, has it been independently reviewed, and who will own it during construction and recommended independent validation whenever more than about two years have passed since the design was completed. 

Questions from participants covered risk allocation at the planning stage, the level of detail needed in feasibility studies and preliminary designs, the drafting of Employer's Requirements and the practicalities of early market engagement. Panellists suggested a simple test for allocating risk to the contractor, whether it can realistically be priced and managed and stressed that employers need to understand local market conditions, Asked what participants should do differently on their next project, Nadar summarised three actions: invest in upfront homework, make deliberate and informed choices on procurement strategy and contract form while respecting the FIDIC Golden Principles, and make sure the right people with a shared understanding of the contract are around the table, including through joint contract training for employer, Engineer and contractor teams. 

The webinar concluded the 2026 FIDIC-CICA series, which opened in March with a session on the Engineer's key role in contracts and continued in June with a focus on the FIDIC Emerald Book. Many of the themes raised, including early market engagement and good project preparation, will be explored further at the FIDIC International Contract Users' Conference and Awards 2026 in London from 30 November to 3 December. FIDIC is also co-hosting the 2026 ICC-FIDIC Conference on International Construction Contracts & Dispute Resolution in Bogotá, Colombia, on 15-16 October, while CICA's annual conference takes place in Paris on 4 November. 

Watch the recording of the webinar below. 

Related news

Ghana to host FIDIC Africa Infrastructure Conference 2026

10-Apr-2026

FIDIC and Blue Dot Network partner to advance quality infrastructure certification

22-Sep-2026

FIDIC CEO Susanna Zammataro joins Engineering Influence podcast

20-Jul-2026

FIDIC and International Transport Forum strengthen collaboration

06-May-2026